On average, we can deliver a house set to the construction site three months after the delivery contract has been signed. The constructive design of the building takes most of that time. After all the important dimensions and details of the building have been agreed upon on the approval drawings, we can start preparing production and installation drawings. At the same time we place orders for materials that take longer to deliver and for other accompanying products, such as windows, balcony and external doors, laminated timber structures, etc. This is also one of the reasons why it can be very costly to make alterations to the drawings after the approval drawings have been signed.
The production time for an average sized house (150 to 200 m²) at the factory, including preparations for production, is two weeks.